Power Transmission & Distribution System

Electricity transmission is the process by which large amounts of Electricity produced at power plants (such as hydro, geothermal, thermal and wind), is transported over long distances for eventual use by consumers. Due to the large amount of power involved, and the properties of Electricity, transmission normally takes place at high voltage (132-kilovolt or above) to reduce losses that occur over long distances. 

Electricity is usually transmitted to a substation near a populated area. At the substation, the high voltage Electricity is converted to lower voltages suitable for consumer use, and then transmitted to end users through relatively low-voltage Electricity distribution lines that are owned and operated by the national Electricity utility.  In Kenya, Kenya Transmission Company (KETRACO) Limited, 100% state owned corporation incorporated, in 2008 has   been mandated to plan, design, construct, own operate and maintain high voltage electricity transmission grid and regional power interconnectos infrastructure that will form the backbone of the National Transmission Grid.

In carrying out this mandate, the Company is expected to develop a new and robust grid system in order to:

  1. Improve the quality and reliability of electricity supply throughout the country;
  2. Provide electricity to areas that are currently not supplied from the national grid;
  3. Provide a link with neighboring countries in order to facilitate power exchange and develop electricity trade in the region;
  4. Reduce transmission losses that currently cost the country about US$17 million per year; and
  5. Reduce the cost of electricity to the consumer by absorbing the capital cost of transmission lines since they will be fully funded by the government of Kenya.

The voltage rating of the transmission lines include 132kV, 220kV, 400kV and 500kV (HVDC) covering *** km of which 2,364km is owned and operated by KETRACO.

Kenya’s existing transmission lines and substations together with their transformation capacity is as provided.

Table: Kenya’s existing substations together with their transformation capacity

ItemSubstation NameVoltage LevelsTransformation Capacity, MVATotal MVA Capacity
1Galu132/33kV2*2346
2Malindi220/33kV1*2323
3Garsen220/33kV1*2323
4Lamu220/33kV1*2323
5Rang'ala132/33kV2*2346
6Kegati132/33kV2*2346
7Kitale132/33kV2*2346
8Githambo132/33kV1*2323
9Isiolo132/33kV1*2323
10Mangu132/66kV1*6060
11Gatundu132/33kV1*2323
12Meru132/33kV1*2323
13Mwingi132/33kV1*2323
14Garissa132/33/11kV2*7.515
15Kindaruma132kV--
16Konza132/33kV1*2323
17Sotik132kV--
18Bomet132/33kV1*2323
19Machakos132/33kV1*2323
20Ishiara132kV--
21Kieni132/33kV1*2323
22Awendo132/33kV2*2346
23Sultan-Hamud132/33kV1*2323
24Suswa220kV--
25Ndhiwa132/33kV1*2323
26Wote132/33kV1*2323
27Olkaria 1AU220/132kV1*105105
28Sondu132kV--
29Menengai132kV--
30Olkaria V220kV--

Table: Kenya’s existing transmission lines with respective loading

Voltage(kV)Line DesignationNumber of circuitsConductorThermal rating (MVA) - 100% LoadingRating (MVA) - 80% Loading
132Rabai-GaluS/CACSR Lynx112.990.3
132Kamburu-IshiaraS/CACSR LGJ-300/50150120
132Ishiara-MeruS/CACSR LGJ-300/50150120
132Meru-IsioloS/CACSR Lynx112.990.3
132Kindaruma-MwingiS/CACSR Lynx112.990.3
132Mwingi - GarissaS/CACSR Lynx112.990.3
132Mangu-GithamboS/CACSR Lynx112.990.3
132Mangu-GatunduS/CACSR Lynx112.990.3
132Sotik-BometS/CACSR Lynx112.990.3
132Chemosit- SotikS/CACSR LGJ-300/50150120
132Sotik-KegatiS/CACSR LGJ-300/50150120
132Mumias-RangalaS/CACSR Lynx112.990.3
132Sondu-KisumuS/CACSR Lynx112.990.3
132Sangoro-SonduS/CACSR Lynx112.990.3
132Kegati-AwendoS/CACSR Lynx112.990.3
132Eldoret-KitaleS/CACSR Lynx112.990.3
132Awendo-NdhiwaS/CACSR Lynx112.990.3
132Ishiara-KieniS/CACSR Lynx112.990.3
132Sultan-WoteS/CACSR Lynx112.990.3
132Konza-KatoloniS/CACSR Lynx112.990.3
132Menengai-SoiloD/CACSR Lynx112.990.3
220Rabai-Kakuyuni (Malindi)S/CACSR DIN-300/50255204
220Kakuyuni (Malindi)-GarsenS/CACSR DIN-300/50255204
220Garsen-LamuS/CACSR LGJ-300/50255204
220Olkaria IV - SuswaD/CACSR Canary326260.8
220Olkaria I AU - SuswaD/CACSR Canary326260.8
220Suswa - IsinyaD/CACSR Condor16481318.4
220Suswa-LoiyangalaniD/CACSR Condor16481318.4
220Isinya - RabaiD/CACSR Lark14491159.2
220Suswa- Embakasi---
220Olkaria II - Olkaria 1AU---
KEY:
S/C – Single Circuit,
D/C – Double Circuit

In the 2018-2038 Transmission Master Plan, KETRACO Plans to construct an extra 8469KM of transmission lines.

Planned Expansion of Transmission Network
Regional Interconnectors

Kenya is working towards interconnecting with its neighbors in the Eastern Africa Power Pool. As part of the plan a number of transmission lines are being developed.

Map Showing Regional Interconnectors
132km 400kV Lessos-Tororo line (Kenya – Uganda Interconnector)

This is a double circuit transmission line that evacuates up to a maximum of 1,200MW from the existing Lessos substation (Kenya) to the Kenya – Uganda border near Tororo substation (Uganda).

It is currently operating at 220kV but will be upgraded to 400kV to facilitate higher power transfer.

It is a part of the interconnection of Electric Grids of the Nile Equatorial Lakes Countries Project (NELSAP).

This cross boundary energy trade will in the long run facilitate power trade within the countries in the Eastern Africa Power Pool (EAPP). It is currently 55% complete.

612km 500kV Eastern Electricity Highway Project (Ethiopia – Kenya Interconnector)

This is a HVDC bi-pole transmission line that will evacuate up to a maximum of 2,000MW from the 400kV substation at Wolayta-Sodo (Ethiopia) to the Suswa 400kV substation (Kenya).

It will enable power trading within the Eastern Africa region and eventually to the Southern Africa Power Pool (SAPP). It is currently 98% complete with the estimated completion date being 31st October 2020.

96km 400kV Kenya – Tanzania Interconnector

This is the Kenyan component of a 2000km double circuit transmission line that will run from Isinya (400kV substation) through Namanga (400kV substation) to Arusha, Tanzania to Zambia. It will act as a link to the SAPP providing opportunities for power trade between SAPP and EAAP. It is currently 67% complete with the estimated completion date being 30th June 2021.